Migrationcenter · Plan

Plan Review

Thu 15 Oct
Finish, likely (P50)
8.7 working days from Mon 5 Oct
Tue 20 Oct
Finish with buffer (P90)
+35% for variability
553 h
Machine-hours
1440 conversions approved
100%
Worker utilization
4 workers busy, on average

Batches · approve to schedule

drafted by the frontier LLM on aliases
BatchItemsMachine-hoursStartsFinishes (P50)
Bracket family
P-0001 – P-0600
600 (69 to cleanse)231.4Mon 5 Oct 08:00Thu 8 Oct 17:53
Hinge sub-assemblies
P-0601 – P-1440
840 (101 to cleanse)321.6Thu 8 Oct 17:49Thu 15 Oct 18:27
Legacy fixtures
P-1441 – P-2400
960 (145 to cleanse)356.1not approved—

Schedule · 4 workers

Licence-bound: 4 licences for 6 machines; 2 machine(s) idle
W01
W02
W03
W04

Burn-up · actual vs forecast

Sample actuals

As of working day 3 (Thu 8 Oct): 433 converted against 463 planned, -30 (-6%) behind. At the current pace (×1.13 of planned minutes) the wave finishes Fri 16 Oct, against Thu 15 Oct planned and Tue 20 Oct with the buffer.

Forecast (P50)Forecast with buffer (P90)ActualAt current pace
Show the numbers
Working dayForecast (P50)With buffer (P90)Actual
0000
1232172206
2381341362
3455398429
4711465—
5943632—
61104798—
71181972—
812571098—
914401152—
1014401205—
1114401265—

What if · working days to finish by worker count

Beyond about 6 workers, each extra one saves less than 3% of the single-worker time